CRITICAL PATH METHOD (CPM) APPLICATION IN TIME MANAGEMENT OF THE MALAKA REGENCY OFFICE BUILDING PROJECT

Authors

  • Thomas Aquino Seki Universitas 17 Agustus 1945 Surabaya
  • Andi Patriadi Universitas 17 Agustus 1945 Surabaya
  • Sajiyo Sajiyo Universitas 17 Agustus 1945 Surabaya

DOI:

https://doi.org/10.46799/ijssr.v5i2.1234

Keywords:

critical path method, project scheduling, time optimization

Abstract

The construction of the Malaka Regency Regent's Office has faced significant challenges, including frequent delays in project completion due to various factors such as design changes, unpredictable weather conditions, labor shortages, and inadequate materials or equipment. These issues have led to inefficiencies in time and cost management, emphasizing the need for effective project management strategies. This study applies the Critical Path Method (CPM) to analyze the project timeline, identify the critical path, and propose measures for project acceleration. By employing CPM, the project schedule was meticulously reviewed and optimized, resulting in a reduction of the initial planned duration from 180 calendar days to 100 calendar days. This acceleration was achieved by minimizing lag times between critical activities, reallocating resources, and implementing time-cost trade-off strategies, all without compromising the quality or scope of the project deliverables. The results demonstrate the effectiveness of CPM in streamlining construction project timelines and mitigating delays. Additionally, this study provides a practical framework for addressing time and cost overruns in construction projects, particularly in the context of public infrastructure development. By highlighting the integration of project management tools like CPM, this research contributes to the broader understanding of efficient scheduling practices and offers actionable insights for similar projects in the future.

References

Asmi, N. (2019). “Analisis Pengendalian Biaya Dan Waktu Pada Perbaikan “Analisis Pengendalian Biaya Dan Waktu Pada Perbaikan Rekontruksi Jalan Metropolitan Makassar ’’. Jurnal Teknik Sipil, P.1-30.

Chen, Q., Feng, H., & de Soto, B. G. (2022). Revamping construction supply chain processes with circular economy strategies: A systematic literature review. Journal of cleaner production, 335, 130240.

Fauzi, M. F. ( 3 September 2024). Analisa Penjadwalan Proyek Menggunakan Cpm Dan Pert Pada Proyek Pembangunan Gedung Koni Jakarta Pusat. Jurnal Teknik Dan Teknologi Indonesia, Vol. 2 .

Gurmu, A. T., & Aibinu, A. A. (2017). Construction equipment management practices for improving labor productivity in multistory building construction projects. Journal of Construction Engineering and Management, 143(10), 04017081.

Hendriyani, I. (2023). Penerapan Metode Cpm Dan Pert Pada Penjadwalan Proyek Pemasangan Pipa Di Perumahan Graha Wiyata Asri Balikpapan. Jurnal Transukma, 236-242.

Lokajaya, I. N. (2019). Analisis Pengendalian Waktu Dan Biaya Pada Proyek Peningkatan Jalan Dengan Metode Cpm Dan Pert. Jurnal Teknik Industri, Vol. 16 No. 2, Hal. 104-125.

Marwan1, A. ( (2024)). Optimasi Waktu Pelaksanaan Pada Manajemen Proyek Pembangunan Gedung Poltekkes Jurusan Farmasi Tahap 1 Dengan Metode Cpm Dan Pert . Journal Of Industrial Engineering Tridinanti, Volume 02, Nomor 01.

Klau, M. J., Sajiyo, Tjendani, H. T. (2024). Time Acceleration Analysis Using The Time Cost Trade Off Method On The Wheat Silo And Pellet Silo Structure Repair Project Phase Iii In Surabay. International Journal On Advanced Technology, Engineering, And Information System(Ijateis), Volume 3, No. 3, 385-395, 2024.

Srivastava, A., Jawaid, S., Singh, R., Gehlot, A., Akram, S. V., Priyadarshi, N., & Khan, B. (2022). Imperative role of technology intervention and implementation for automation in the construction industry. Advances in Civil Engineering, 2022(1), 6716987.

Sutrisno. (April 2023). Implementasi Metode Cpm, Crashing Dan Pert Pada Penjadwalan Proyek Pembangunan Masjid Dan Asrama Yatim Piatu Barokah Amanah Mustaqbal. Jurnal Serambi Engineering, Volume Viii, No.2 Hal 5390 - 5400.

Suwarno, E. (2024). Analisis Evaluasi Manajemen Waktu Dan Biaya Menggunakan Metode Cpm, Pert, Dan Tcto Pada Pelaksanaan Lapis Pondasi Atas (Lpa) Proyek Jls Lot 6

Tulungagung—Trenggalek. Jurnal Inovasi Teknologi Dan Edukasi Teknik, 10.17977/Um068.V4.I7.2024.

Victor. (2021). Analisis Manajemen Biaya Proyek Pada Proyek Konstruksi Di Tangerang. Prosiding Ceedrims, 978-602-361- 385-4 .

Wahananto, A., Witjaksana, B., Patriadi, A. (2024). Analisis Sistem Penyediaan Air Bersih Kampung Kasai Kecamatan Pulau Derawan Kabupaten Berau. Jurnal Teknika (Jurnal Fakultas Teknik Universitas Islam Lamongan), Vol. 16, No. 2, Hal. 113-118.

Yuwono, W. (Agustus 2021). Kajian Metode Pert-Cpm Dan Pemanfaatannya Dalam Manajemen Waktu Dan Biaya Pelaksanaan Proyek. Journal Of Economic, Management, Accounting And Technology (Jematech), Vol. 4, No. 2 2622-8122.